Millwood Avenue project timeline

Posted: October 12, 2013

This is the construction timeline Shenandoah University has proposed for the Millwood Avenue Public Improvement Project. Phase 1 is street construction work; Phase 2 is landscaping work.

October: Presentation of landscaping and gateway conceptual plan at City Council work session.

November: City Council approval of conceptual plan.

February to March: Obtain contractor for Phase 1 improvements. Final landscape design plans received.

April 2014: Completion of agreements for utility relocation.

May 2014: City authorizes start of Phase 1 construction, which is anticipated to last 150 days.

November 2014: Start of Phase 2 work.

Spring 2015: Installation of final landscaping elements to complete Phase 2.

Source: Shenandoah University